Construction Updates

  1. January 2015 to Early 2016

    The above grade structure continues to advance on schedule, with the final podium floor slab (level 6) on track for completion in late May 2015. Structural work will continue for the remainder of the year and into 2016. Curtain wall installation will be commencing shortly and continue into 2016 as well.

  2. August to December 2014

    Excavation is nearing completion and below grade structural work has started. The raft slab was poured mid-July and the slab on grade is on track for completion at the end of August. With two tower cranes now operational on site, below grade structural work will continue until January 2015.